Refinery of Baiji Project: (Ministry of Oil) – 2021
EPC for synchronization and SCADA System for uninterruptable power generation project 25MW
• Our Scope contains the following activities:
– Engineering and design The SCADA system of the project as per the standards and client specification.
– Procurement and installation for all SCADA system and synchronization system to synchronizing 25 power generators distributed on 6 units with full monitoring and controlling on them from the Central control Room.
– Design and construct interlock system to prevent any mistake may be occurred by operators.
➢ Our client in this project is Ministry of Oil.